试题47(2010年上半年试题71)
(71) assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.
(71)A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
试题47分析
定性风险分析利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受水平),对已识别风险进行优先级的评估。
试题47答案
(71)B
共有条评论 网友评论