试题50(2010年下半年试题71)
Project schedule management is made up of six management processes including: activity definition,activity sequencing, (71) ,and schedule control by order.
(71)A.activity duration estimating,schedule developing,activity resource estimating
B.activity resource estimating,activity duration estimating,schedule development
C.schedule developing,activity resource estimating,activity duration estimating
D.activity resource estimating,schedule developing,activity duration estimating
试题50分析
项目进度管理由6个管理过程组成,依次包括活动定义、活动排序、活动资源估算、活动历时估算、制定进度计划和进度控制。
试题50答案
(71)B
共有条评论 网友评论