试题37(2008年下半年试题72)
Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling,executing,and monitoring and controlling the project work.
(72)A.reviewing
B.estimating
C.auditing
D.expecting
试题37分析
项目工作包通常分解为更小的称为活动的组件,以便提供一个基线,用来估算、计划、执行、监控项目工作。
试题37答案
(72)B
共有条评论 网友评论