试题38(2008年下半年试题73)
The Estimate Activity Resource process is closely coordinated with the (73) process.
(73)A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
试题38分析
活动资源估算过程与成本估算过程密切相关。
试题38答案
(73)A
The Estimate Activity Resource process is closely coordinated with the (73) process.
(73)A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
试题38分析
活动资源估算过程与成本估算过程密切相关。
试题38答案
(73)A
共有条评论 网友评论