试题40(2008年下半年试题75)
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
(75)A.analyze
B.track
C.level
D.extend
试题40分析
项目计划制定通常是一个迭代的过程,它决定了项目活动和里程碑的计划开始与结束时间。制定计划可能需要评审和修订历时估算和资源估算的结果,以便创建一个被认可的项目计划,该计划可以作为一个跟踪项目进展的基准。
试题40答案
(75)B