Many of the activities performed during the preliminary investigation are still being conducted in (71) but in much greater depth than before. During this phase,the analyst must become fully aware of the (72) and must develop enough knowledge about the (73) and the existing systems to enable an effective solution to be proposed and implemented. Besides the (74) for process and data of current system,the deliverable from this phase also includes the (75) for the proposed system.

(71)A.analysis phase
B.design phase
C.implementation phase
D.maintenance phase

(72)A.main symptom
B.root problem
C.final blueprint
D.data specification

(73)A.hardware environment
B.testing environment
C.software environment
D.business environment

(74)A.logical models
B.physical models
C.design models
D.implementation models

(75)A.hardware and software specification
B.system performance specification
C.formal requirements definition
D.general problem statement

试题41分析

在初步调研时完成的许多活动在分析阶段还要继续进行,只是比以前更深入地去做。在这个分析阶段,系统分析师一定要充分注意到问题的根源,并且充分掌握关于业务环境和现行系统的知识,以提交和实施一个有效的解决方案。除了提交现行系统的过程和数据的逻辑模型外,这一分析阶段的交付物还包括推荐系统的正式需求定义。

试题41答案

(71)A

(72)B

(73)D

(74)A

(75)C