试题54(2010年下半年试题75)
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
(75)A.independent resource
B.individual work load
C.work milestone
D.work package
试题54分析
创建WBS意味着将一个大的项目分解为更小的组成部分,直到将项目可交付物分解至工作包的层次。
试题54答案
(75)D